Fort Sumter Pier


Project Name: Fort Sumter Pier
Location: Charleston, South Carolina
Contract Number: 1443CX501097902
Phase 1 involved the construction of a substantial land-side and waterside containment system to prevent the offsite migration of contaminants, establishment and maintenance of an Exclusion Zone, removal of subsurface obstructions and contaminants, design and construction of a 200 foot long temporary trestle to support a 225 ton crane, and driving 320 concrete piles 14 inch x 100 foot long. The pile driving and concrete work associated with this complex project is indicative of the type of superior workmanship that Triton work crews produce. Triton Marine completed this difficult project ahead of schedule and with superior results. Phase II involved the construction of a cast in place concrete Pier and utilities for the future tour boat facility to be constructed for Fort Sumter National Monument.